# Used soil cement to create sharp edges on upper interior trench. | # Used soil cement to create sharp edges on upper interior trench. | ||
# Covered 100 % with 15mil underlayment requires UFER to be placed outside of trench or separate driven rods. | # Covered 100 % with 15mil underlayment requires UFER to be placed outside of trench or separate driven rods. | ||
# Make sure anchor bolts are placed properly during pour. They will need to be adjusted as pouring will move them. | |||
Framing Notes: | Framing Notes: | ||
# Cuts at 3.56 degrees for upper walls. | |||
# Use wall jacks to lift walls. | |||
# |
Revision as of 04:33, 6 March 2023
Foundation Notes-
- Rebar chairs allow bending up towards center, making rebar too close to surface at center of slab. Remedy:
- Use twisting tool for tying rebar.
- Rent bender (weekly rate) and cutter for rebar.
- Used soil cement to create sharp edges on upper interior trench.
- Covered 100 % with 15mil underlayment requires UFER to be placed outside of trench or separate driven rods.
- Make sure anchor bolts are placed properly during pour. They will need to be adjusted as pouring will move them.
Framing Notes:
- Cuts at 3.56 degrees for upper walls.
- Use wall jacks to lift walls.